Client story · Acreage and rural · Grants Pass
Three wells, a river right and an unbuilt power line
A 5-acre RR-5 parcel came with three wells, a river-water right, an unbuilt power work order and an unpermitted cabin. We listed every open question before the buyer committed.
The situation
The parcel had a lot going on: three wells, a river-water right with an intake pipe on federal land, a power-line work order a prior owner opened but never built, and a cabin without permits or septic completion records.
What we did
We worked through each item: the BLM right-of-way transfer for the intake and proof the annual rent was current, the recovery pauses in the well tests, the status of the power extension, and the septic records for the cabin.
The outcome
The buyer knew the legal standing of the water, power and buildings, and what each open item would take to resolve, before committing to the purchase.